7.Lock the unit into the rack
The payShield 10K is physically locked into the rack via the two key locks located on the front of the unit.
NOTE: Each lock has its own key and each key is owned by a security officer.
To physically lock the unit into the rack, each key holder inserts their key into their respective lock and turns the lock to the locked position.
8.. Connect the Fiber optic cable, power cable and then turn the unit on
NOTE: When power is applied to the unit, there is a period of time before the unit is operational and either the console
or payShield Manager is available.
9.Configuring the payShield 10K
The payShield 10K can be configured via payShield Manager or via the console terminal.
NOTE: For payShield Manager and Host operation, the payShield must be ONLINE, i.e., the front panel keys are in the locked position.
•USB to 25 pin parallel printer cable
•payShield Manager smart cards
•payShield Manager Starter Kit
•payShield Manager Reader
•Confirm that you are using the appropriate Fiber optic cable and connector type, as defined in the tables in Step 4
•Plug the cable connectors into the LC connectors of Port 1
•Connect the power supplies
•Push the on/off power switch located on the back of the unit; the unit has power when the power switch is pressed in
To ensure that temperature ranges are not exceeded, consider airflow and temperature when installing the HSM in the rack. Once
installed, ventilation holes must not become obstructed, as that would reduce the air flow through the unit.
3.Insert the SFP
•Remove the dust cover from Port 1. Port 2 is not used.
•Install the SFP by sliding it into the housing. When the latch engages,
it clicks.
NOTE: Handling the SFP is a delicate operation -
take care not to damage the transceivers. Observe
standard Electrostatic Discharge (ESD) precautions
for handling electronic components.
•FICON interface cable - see tables below
For payShield Manager:
•A standard Ethernet cable for the Management Port
•A standard desktop PC or laptop with a web browser supported
by payShield Manager, (e.g. Chrome or Firefox)
For the console terminal:
•Wait for the health LED to turn solid white or solid red before proceeding
•Once the payShield is powered up, the FICON interface performs a Power On Self-test. The yellow LED indicates port activity while
the green LED indicates firmware operation. Refer to the payShield 10K Installation and User Guide for information regarding
additional LED indications
•For additional instruction, refer to the payShield Manager Quick start guide, the payShield 10K Installation and
User Guide, and the payShield 10K Console Guide
NOTE: Based on your order, additional items may be
included in your shipment. In certain circumstances,
the security keys and smart cards may be delivered
under separate cover to the two designated keyholders.
Optional accessories:
Operating temperature
Storage temperature
Transportation temperature
Operating humidity
Transportation humidity
Altitude
Overall rack dimensions (WxDxH)
Maximum Operating Power Consumption
1U rack 19” x 29” x 1.75” (482.6mm x 736.6 mm x 44.5mm)
80W
Storage humidity
4.Gather additional equipment
For printer ports:
Unpack the Thales box containing the Thales Universal Rack Mount Kit. The Mount Kit contains 2 rails and 10 M4 x 6 mm screws.
Remove inner rail from rack mount assembly.
•Position the inner rail on the side of the product with the safety catch toward the rear
•Align the rear hole of the rail with the rear hole on the chassis and attach using the M4 x 6mm screws provided
•Align the other 4 holes with the counter sink in the rail with the corresponding holes in the chassis, insert the M4 x 6mm screws, and tighten all the screws
•Repeat this to attach the second inner rail to the other side of the chassis
NOTE: The 1U 1000 mm Universal Rack Mount Kit is pre-assembled for use with square hole and unthreaded round hole racks.
This rack kit is suitable for racks and cabinets where the depth between front and rear posts is in the range 685.8mm – 939.8mm.
5.Determine your location
•Printer Interface cable (Optional) - Printer communication is via
USB peripheral cable for payShield Manager
For FICON ports:
•A standard desktop PC or laptop using terminal emulation software
Adjust rail length. (The rails support a range of rack mounting depths.)
Loosen the two rear retaining plate screws to enable the rear bracket to be extended.
Install outer rails into the rack.
•With both the left and right bearing retainers moved the entire way forward, align the inner rails mounted on the product with
the outer rails mounted in the rack
•You may need to apply gentle pressure to the ends of the inner rails to align them with the outer rails
•Slide the product into the rack until the safety latches engage
Push the safety catches in on both sides and slide the product fully into the rack. When sliding the unit into the rack for the first time, the last
few inches of travel may experience some resistance as the bearing retainers meet their backstops. The resistance can be overcome by applying
slightly more force to the front of the unit to achieve full insertion into the rack.
-100m to 2000m AMSL (Above Mean Sea Level)
5 – 93% (Relative non-condensing at 40°C)
5 – 93% (Relative non-condensing at 30°C)
-5°C to 45°C
-25°C to 70°C
5 – 85% (Relative non-condensing at 30°C)
0°– 40°C
6.Mount the rack
•Slide the inner rail until the safety catch locks
•Depress the safety catch and continue sliding to separate the inner and outer rails
Attach inner rail to the chassis.
•Align the bracket marked “FRONT” with the holes in the front post
•Once aligned, push the bracket forward until the snap mechanism engages
•Slide the rear bracket towards the rear post of the rack
•Align the bracket with the holes in the rear post at the same vertical position used for the front and snap it in
•Tighten the two rear retaining screws
IMPORTANT: Slide the bearing retainer all the way forward to avoid damaging the rail kit when the product is installed.
Insert product into the outer rails.