3.0 INSTALLATION
3.1 Carefully remove the packaging from each item and check for damage. Immediately report
any damage to Exheat Industrial Ltd.
3.2 Move the equipment by either crane or fork lift truck, using suitable rated lifting slings to
prevent damage.
All lifting tackle/equipment must have a safe working load (SWL) capacity in excess
of that of the equipment weight and include for snatch factors etc.
The slings or ropes must be long enough to keep the angle between the slings/ropes
and the top of the equipment greater than 90°
Ensure that the destination position is free from obstructions.
Move the equipment into position and set the load down carefully and without
bumping.
3.3 The radiator should be securely fixed in position with the wall brackets supplied and all
terminal connections checked for tightness before energising. Please refer to APPENDIX B &
C for all mounting point dimensions.
3.4 The correct installed orientation is with the terminal box at the bottom of the radiator.
3.5 The installer or end user shall ensure that the unit has free and unrestricted air flow to allow
natural convection to occur at all times. DO NOT COVER the radiator and do not allow
anything to rest on or against it. If a protective guard is required, only Exheat Industrial Ltd’s
design is pre-approved and tested with the FLR range.
3.6 At no time is the ambient temperature to be allowed to rise above 40°C.
3.7 FLRA radiators supplied with an externally adjustable thermostat must be limited and set to a
maximum of 25°C.
4.0 ELECTRICAL SUPPLY CONNECTION
4.1 Refer to wiring diagram APPENDIX A.
4.2 The cable entry is positioned on the bottom of the terminal box.
4.3 Before connection ensure that the supply corresponds with that specified on the rating label.
4.4 Ensure that the sizes and types of cables to be used are suitably rated for the load and
temperature of the unit.
4.5 Each heater must be protected by a suitably rated over current device and earth leakage
circuit breaker device. See section 5 below for earthing details.
4.6 The cables must enter the heater terminal box via suitably certified cable glands (not
supplied) and be fitted by a qualified person. Any unused entries should remain plugged with
the factory fitted certified Ex d plugs.
4.7 The cover of the terminal box is removed after releasing the 3 socket head screws in the
cover. When re-fitting ensure that the ‘o’ ring seal is in good condition and correctly located.
The main cover mating and spigot faces MUST be kept clean and free from any debris at all
times.
4.8 After re-fitting, the gap between the cover and the body must be checked to ensure that it
does not exceed 0.15mm.
4.9 The installer or end user must connect to the Exheat Industrial Ltd supplied terminals within
the terminal box - DO NOT connect to or disturb factory fitted wiring.
4.10 WARNING – Silica gel bags must be removed before the heater is energised.