Installing supports for header hoses:
1) Trays are positioned directly
above the rank of openers that they
serve. Position center trays at an
offset fore/aft so they aren’t directly
in line with wing trays (see Photo
B) (they need clearance when wings
fold). Center front trays are spliced
on 40 & 42/43-ft models; center
rear (low-profile) trays are spliced
on all CCS drills. Locate the halves,
and prepare* to fasten them
together using splicer (sheet metal
piece that fits on underside of tray
to join the halves), and ½" x 3/4"
button-head bolts and flange
locknuts on bottom (button-heads
on inside, where hose will lie), and
with 5/16 x 3/4" hex-head bolts, flat
washer & locknuts on the side
(upright portion of tray). Be sure to
fasten the tray ends together that
have only 4 holes, not the series of
holes which belong on outer ends of
tray (see Photo C). (*Some tray
splices are most easily joined after
sliding each half into position, rather than pre-assembling—especially center-rear.)
2) For the front center trays, locate brackets #0002 and place
them on the drill’s center-section frame, over the fore/aft tubes
(see Photo E—it’s the same concept for all these brackets,
except the rear
center where the
bracket comes
up from
underneath).
Slide the 8" bar
onto the
brackets’ studs
from
underneath, and
then ½" flange
locknuts—but
don’t tighten yet. Fasten front center tray to front
brackets with ½" x 3/4" button-head bolts using blue
Loctite (provided). (Loctite isn’t needed on anything
secured with a flange locknut.) Center rear rank
uses brkt #0007 which goes onto fore/aft frame tube
Center section,
rear.
Brkt #0007.
Photo E. RH wing: front, outer end. Brkt #0004.
Tray is attached via ½ x 3/4" buttonhead bolts
threaded into U-bracket. Assembly pulled up
off the frame tube for viewing.
Photo B. Yellow lines show the offset of tray position on center vs
wings. This is an 1895, hence the extra towers and extra rank. All
trays go on top of frame tubes except center rear on CCSs.