cleanAIR CAP577 Installation and operating instructions

INSTALLATION GUIDE
GETTING READY CAP577
TOOLS AND EQUIPMENT REQUIRED FOR ASSEMB Vertical Flow
8605 Wyoming Avenue N. • Minneapolis, MN 55445
763-425-9122 • 800-423-9728 • Fax: 763-425-2004
E-Mail: [email protected]
www.cleanairproducts.com
200706
Engineering Solutions with Value and Integrity
INSTALLATION & MAINTENANCE INSTRUCTIONS FOR
CAP577
Vertical Flow Softwall Modular Cleanroom

8605 Wyoming Ave. N. •Minneapolis, MN 55445 • 763-425-9122 • 800-423-9728 • Fax 763-425-2004
210226
INSTALLATION & MAINTENANCE GUIDE
CAP577
Vertical Flow Softwall Modular Cleanroom
www.cleanairproducts.com
2
SUPPLIED HARDWARE
•One or more A-frame style ladders that allow workers safe access above the cleanroom ceiling.
•**A sheet good lift can be useful to help position the filters in the ceiling.
**Review the details of the clean rooms design and become familiar with the layout and
optional items that have been included. Many of these options affect the build process.
Relevant documents can be found on the following pages. **

8605 Wyoming Ave. N. •Minneapolis, MN 55445 • 763-425-9122 • 800-423-9728 • Fax 763-425-2004
210226
INSTALLATION & MAINTENANCE GUIDE
CAP577
Vertical Flow Softwall Modular Cleanroom
www.cleanairproducts.com
3

Please observe the following information related to the
product:
1) Read this guide before installing and/or operating
the unit and retain for future reference.
2) Observe warnings associated with handling,
installing, using, and maintaining the CAP577.
3) Follow all instructions for set-up, operation, and
use.
4) Operate ONLY from the type of power source
indicated. If you are unsure of the type of power
available to you, contact your dealer or power
company.
5) This unit may be equipped with a polarized
alternating current (AC) plug with one blade wider
than the other. This plug will only fit into the power
outlet in one way for safety reasons. If the plug does
not fit, call an electrician to replace the outlet. DO NOT
REMOVE THE ROUND GROUNDING TERMINAL. THIS
UNIT MUST BE GROUNDED FOR SAFETY REASONS
AND FOR PROPER OPERATION.
6) Do not place power cords (optional) where they will
be damaged, especially near the outlet, the plug, or
where the power cord exits the unit.
7) Overloading outlets and/or extension cords can
result in fire and/or electrical shock.
8) ONLY use parts supplied or authorized by the
manufacturer. Substitutions may result in fire,
electrical shock, or other safety hazards.
Safety Warnings
1) NEVER expose the assembly to moisture or rain.
2) If the unit gets wet, disconnect the power at the
source and have an authorized service inspection
before using it again.
3) Do not pull on the optional power cord to unplug
the unit, and never handle the cord with wet hands.
4) Do not clean the unit with flammable chemicals.
5) Do not expose to explosive or hazardous vapors or
materials.
6) Make sure the unit is well supported to prevent
falling.
7) Do not block airflow to the unit.
8) Disconnect the power before servicing.
9) Do not operate below 0 degrees Fahrenheit or
above 110 degrees Fahrenheit.
10) This unit is designed to operate in a non-
hazardous (non-explosive) environment with non-
condensing air.
11) NEVER put objects into the blower.
12) Do not operate without metal blower guard.
13) Review application with your safety commissioner
for proper use

8605 Wyoming Ave. N. •Minneapolis, MN 55445 • 763-425-9122 • 800-423-9728 • Fax 763-425-2004
210226
INSTALLATION & MAINTENANCE GUIDE
CAP577
Vertical Flow Softwall Modular Cleanroom
www.cleanairproducts.com
8
GETTING READY: UNPACK BEAMS
Locate the area that the clean room is going to be assembled and mark out on the ground the final dimensions of
the room with tape or suitable substitute. This is helpful in a later step to ensure the room is “true” and square.
** ONLY USE IPA AS CLEANER ON PAINTED METAL SURFICES TO AVOID RESIDUES THAT MAY CAUSE
ISSUES WITH THE DUAL LOCK ADHESIVE **
Open the beam boxes on the ground and leave the beams on the boxes. Remove and dispose of the shipping blocks
and shipping hardware.

8605 Wyoming Ave. N. •Minneapolis, MN 55445 • 763-425-9122 • 800-423-9728 • Fax 763-425-2004
210226
INSTALLATION & MAINTENANCE GUIDE
CAP577
Vertical Flow Softwall Modular Cleanroom
www.cleanairproducts.com
9
FRAME PREPARATION
Reference your Curtain drawing at the beginning of the manual for the beam layout. On the ground, arrange and
bolt together one section of side beams and their corresponding center beam(s) as seen in the diagram below.
Ensure that the 11/64” holes running along the beams are oriented UP. Keep the beams protected by keeping them
on their shipping boxes. Note the installation order of the washer, lock washer and bolt in the diagram below.
EXAMPLE CURTAIN DRAWING BEAM ASSEMBLY EXAMPLE
ROOM NOTES:
*Larger rooms with more than 4 legs will start by building one “Four Leg Section” of the frame and then add
additional beam sections to the standing structure as described in the FRAME ASSEMBLY section.

8605 Wyoming Ave. N. •Minneapolis, MN 55445 • 763-425-9122 • 800-423-9728 • Fax 763-425-2004
210226
INSTALLATION & MAINTENANCE GUIDE
CAP577
Vertical Flow Softwall Modular Cleanroom
www.cleanairproducts.com
10
LEG PREPARATION
Note the installation order of the washer, lock washer and bolt. Attach the corner brackets (577 Corner Gusset) to
the legs by manually turning the bolt three full threads by hand. This reduces the chances of cross threading when
using a power driver. Assemble the brackets with the open sides towards each other as seen below. Leave the bolts
loose until the legs are attached to the frame.
NOTES: *Rooms over 8’ in height have special Right and Left handed extended Brackets and matching legs

8605 Wyoming Ave. N. •Minneapolis, MN 55445 • 763-425-9122 • 800-423-9728 • Fax 763-425-2004
210226
INSTALLATION & MAINTENANCE GUIDE
CAP577
Vertical Flow Softwall Modular Cleanroom
www.cleanairproducts.com
11
*Rooms with six or more legs will require assembling legs with 3 or 4 brackets. Reference the curtain drawing at the
beginning of this manual for quantity and locations.
*Rooms with casters will require the installation of the casters into the legs. The casters are shipped separately in
the hardware box. Slide the top of the caster insert into the bottom of the leg. If necessary, carefully drive the
insert in with a mallet and dowel.

8605 Wyoming Ave. N. •Minneapolis, MN 55445 • 763-425-9122 • 800-423-9728 • Fax 763-425-2004
210226
INSTALLATION & MAINTENANCE GUIDE
CAP577
Vertical Flow Softwall Modular Cleanroom
www.cleanairproducts.com
12
FRAME ASSEMBLY
Using a cardboard box under the beams, position the Lift so that the fork extensions span under a center beam(s).
Clamp the Frame to the fork extension to aid stability. Position a worker on a ladder at a corner to help carefully lift
the structure to the room height. Position a leg in the corner and bolt the leg bracket and corner strut to the side
beam as shown. Leave the lift in place and repeat this process at each corner.

8605 Wyoming Ave. N. •Minneapolis, MN 55445 • 763-425-9122 • 800-423-9728 • Fax 763-425-2004
210226
INSTALLATION & MAINTENANCE GUIDE
CAP577
Vertical Flow Softwall Modular Cleanroom
www.cleanairproducts.com
13
With all four legs attached use one person on each end to lift the additional side beams into place. Bolt them to the
leg brackets while securing the second side of the corner struts. Check the frames dimensions and the spacing of
the legs at the floor to ensure the room is square while tightening all bolts. It is now safe to remove the lift. Use the
leg levelers to plumb the room.
ROOMS W/ MULTIPLE SECTIONS:
Larger rooms with multiple sections are built by adding
additional sections to the first by following the same
procedure.